M/S. Ganesh Builders And ORS . v. Neelima Co-Op. Hsg. Soc. Ltd.
Sherla V.
fa.892.2001_902.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION FIRST APPEAL NO.892 OF 2001 M/s.Ganesh Star Builders & ors.
... Appellants Vs.
Neelima Apartments Co-op. Hsg. Society Ltd. & anr. ... Respondents a/w FIRST APPEAL NO.890 OF 2001 a/w FIRST APPEAL NO.891 OF 2001 Mr.G.S. Bhat for the Appellants Ms.Jyoti Mistry i/b M/s.S.K. Srivastava & Co. for Respondents CORAM: MRS.MRIDULA BHATKAR, J.
DATE: 23rd DECEMBER, 2015 P.C.:
1.
Parties have filed consent terms, in First Appeal No.892 of 2001, signed by the partner of appellant No.1, Chairman and Secretary of Respondent No.1 and their respective advocates. The partner of the appellant No.1 and the office bearers of the respondents are present. The consent terms are taken on record and marked 'X' for identification. 2.
In view of the consent terms, the learned Counsel for the appellants in First Appeal Nos.890 of 2001 and 891 of 2001 seeks leave to withdraw the two appeals. The appeals are accordingly allowed to be withdrawn and dismissed as such.
1 / 2
fa.892.2001_902.doc 3.
Refund of Court fees as per rules.
4.
Decree to operate as conveyance.
5.
Certified copy expedited.
(MRIDULA BHATKAR, J.) 2 / 2