Calcutta High CourtMAT/2102/2022disposed

Duster Total Solutions Services Pvt Ltd And ANR v. Reliable Facility Services Pvt Ltd And ORS

2022-12-29Hon'Ble Justice Abhijit Gangopadhyay,Hon'Ble Justice Prasenjit Biswas2 pages

20. 29.12.2022 Ct. No.08 cm MAT 2102 of 2022 With CAN 1 of 2022 Duster Total Solutions Services Pvt. Ltd. & Anr. -VersusReliable Facility Services Pvt. Ltd. & Ors. Mr. Kallol Basu Mr. Samik Sarkar ...for the appellants.

Ms. Aparna Banerjee ...for the Respondent No.3 to 6.

Mr. Suddhasatra Banerjee Mr. Soumasho Ghosh Mr. Sagnik Majumdar Ms. Ananya Das ... for the respondent No.1 Life of the tender is only two months.

Learned advocate for the hospital authority submits that there is no allegation against the appellants that he is not working properly or to the satisfaction of the authority. Only two months' life is pending in respect of the contract. For the next contract, tender has been floated by the hospital authority to which the appellant has participated and the respondent No.1 has said that the stage of participation has not arrived as yet. It is open to him whether he would participate in the tender or not. As no adverse report against the appellants is there and the life of the tender work is less than two months from date as stated by the learned

advocate for the hospital authority we do not think that for the coming nearly two months i.e. till 23rd February, 2023 the work should be handed over to the respondent No.1 and, therefore, to this extent, we interfere with the observation of the learned Single Judge and the relevant part of the order is set aside and the appellants will work till completion of the tender period i.e. 23rd February, 2023.

Thus, with this observation and direction the appeal and the connected application are disposed of.

(Prasenjit Biswas) (Abhijit Gangopadhyay, J.)